Proof of concept. This lesson is illustrative, written to show the format the real log will use.

Lessons Learned Log

Wrong breather membrane spec led to £1m of remedial work

Watch outExternal WallTagged: Example LGS Panelised Wall System

What happened

A late supply chain substitution swapped the specified vapour control layer for a vapour permeable breather membrane from the same product family. The delivery paperwork still referenced the original product code, so it was missed at goods in.

Impact

Moisture became trapped in the wall build-up across a batch of occupied units. Residents reported damp and mould before the fault was traced. Once decant costs and remedial works were included, the total came to around £1m.

How it was resolved

An independent moisture survey established how far the problem extended. Affected plots were strip-backed and reinstalled to the correct specification under the warranty provider's oversight, and every plot delivered under the same batch code was audited to rule out further exposure.

The lesson

A product substitution should never be waved through as like for like on a supply chain email. Lock the membrane specification at design freeze, and add a first-fix inspection checkpoint that physically confirms the installed membrane against the drawing reference, not just the delivery note.

Related system record

This lesson is tagged to Example LGS Panelised Wall System.

Back to the Lessons Learned Log